Pine Bluff |
Code of Ordinances |
Chapter 25. SUBDIVISIONS |
Article II. PLATTING PROCEDURES |
Division 1. GENERALLY |
§ 25-40. Schedule of fees.
The following fees shall be paid for plat approval under the provisions of this article:
(1)
Preliminary plat approval
(plus $1.00 per lot) ..... $125.00(2)
Final plat approval ..... 125.00
(3)
R-PUD.
a.
Preliminary approval
(plus $2.00 per lot) ..... 125.00b.
Final approval ..... 125.00
(4)
C-PUD.
a.
Preliminary approval
(plus $2.00 per lot) ..... 125.00b.
Final approval ..... 125.00
(5)
Replat ..... 20.00
(If a preliminary plat is not required; the fee shall be the fee for preliminary plat approval.)
(6)
Lot split ..... 25.00
(Subdivision Regulations, §§ V, XXIV; Ord. No. 6065, § 1, 6-2-03)